Static snapshot. This site serves two different things: 1,988 data centres reported by OpenStreetMap contributors nationwide, and 13 sites Helios infers from Arizona parcel records, exported on July 29, 2026. The first is a map of what has been recorded; the second is an argued hypothesis with an evidence chain. This is a point-in-time export, not a live view. See meta.json or the methodology.

Arizona

State · 82 data centres recorded in OpenStreetMap

Mapped facilities
82
on the map today
Floor area
0.97
km² across 47 buildings
Share of US load
1,001
MW, inferred upper bound
Water
2.18
million gal/day, inferred
21 of these 82 are not mapped as buildings, so no power figure is estimated for them. 16 are campus boundaries covering 7.04 km² of land, and 5 are sites mapped as under construction. The megawatt figure above divides a national total by building floor area, and the area of a land parcel is not floor area. A site still being built consumed none of the electricity that total measures. Both are counted here and left out of the estimate rather than folded into it, so this region's load is understated by however much those represent.

When these appeared on the map

observed, not surveyed
03978201820192020202120222023202420252026
Data centres recorded in OpenStreetMap at the end of each month. The hatched stretch is before 2017-01, when telecom=data_center was not yet in common use — the near-zero readings there describe the tag, not the country. This is a count of what has been mapped, and OpenStreetMap carries no construction dates.
4 of these 82 facilities do not appear in the curve. The chart counts facilities whose appearance was observed in OpenStreetMap's edit history; one mapped before 2012 has no creation edit to observe. The two numbers answer different questions — how many are on the map now, and how many were watched arriving — and neither is wrong.

What the grid here looks like

reported by OSM contributors
Substations
1,033
69 kV and above
Bulk substations
187
230 kV and above
Highest voltage
525
kV, present in this state
Generating capacity
43,660
MW across 279 plants

A facility drawing hundreds of megawatts connects at bulk transmission voltage, so the second figure matters more than the first: forty 69 kV yards are not a substitute for one 500 kV substation. 91 of the plants here carry no capacity tag, so the megawatt total is a floor rather than the region's output.

Proximity is not connection. Nothing here shows that any facility has contracted power from any of these substations. That gets settled in interconnection filings Helios cannot read, and in several regions those queues now run for years. A county showing no substations may have none mapped rather than none standing.

Largest named mapped records

by mapped area
NameOperatorMapped asMapped area m²Share MWFirst mapped
Meta Mesa Data CenterMetaCampus boundary1,379,701—2025-06-20
Microsoft Goodyear Airpark Campusnot recordedCampus boundary1,074,812—2026-06-24
Compass Datacenters Goodyear Campusnot recordedCampus boundary794,157—2026-06-26
Microsoft Goodyear Campusnot recordedCampus boundary732,674—2026-06-24
Google Data CenterGoogleCampus boundary657,471—2025-06-20
Stream Data Centers PHXA Campusnot recordedCampus boundary474,556—2026-06-24
Aligned Data Centersnot recordedUnder construction465,924—2026-06-15
Compass PHX IInot recordedUnder construction460,660—2026-06-15
Apple Mesa Data CenterAppleCampus boundary370,117—2025-12-08
QTS Phoenix 2 Campusnot recordedCampus boundary344,877—not in edit history
NTT PH1 DatacenterNTTCampus boundary293,193—2025-02-04
Stack Infrastructure PHX01 Campusnot recordedUnder construction277,662—2026-06-24
CyrusOne Chandler Campusnot recordedCampus boundary236,824—not in edit history
Stack Infrastructure PHX02 Campusnot recordedUnder construction197,434—not in edit history
Vantage Data Centers AZ1 Campusnot recordedCampus boundary178,744—2026-06-26
Iron Mountainnot recordedCampus boundary163,286—not in edit history
Vantage Data Centers AZ2 Campusnot recordedUnder construction149,195—2026-06-24
EdgeCore Digitalnot recordedCampus boundary148,878—2025-12-08
Apple Data CenterApple Inc.Building124,329128.62018-03-07
Iron Mountain AZP-1Iron MountainCampus boundary117,230—2025-02-07
EdgeConneX PHX02 Data CenterEdgeConneXBuilding60,76862.92023-12-16
Aligned Energy Data Centernot recordedBuilding47,64249.32024-07-09
Iron Mountain AZP-2Iron MountainCampus boundary43,051—2020-12-29
Stream Data Centers PHX-1not recordedBuilding38,39239.72023-10-14
Digital Realty Phoenix PHX15Digital RealtyBuilding27,37628.32023-11-29
PHX-11MicrosoftBuilding23,12023.92023-04-12
PHX-12MicrosoftBuilding22,96023.82026-06-24
PHX-13MicrosoftBuilding22,95923.82026-06-24
PHX-14MicrosoftBuilding22,95723.82026-06-24
PHX-10MicrosoftBuilding22,87123.72023-04-12
Vantage Data CentersVantage Data CentersBuilding22,16522.92024-05-16
QTSQuality Technology ServicesBuilding15,09515.62024-09-15
QTSQuality Technology ServicesBuilding14,54115.02024-09-15
Iron Mountain Records StorageIron MountainBuilding13,54814.02024-01-29
EdgeCorenot recordedBuilding10,48910.82020-05-28
Flexential Phoenix - Deer ValleyFlexentialBuilding10,22210.62024-08-15
GoDaddy - Gilbertnot recordedBuilding8,5308.82020-07-19
EdgeConneXEdgeConneXBuilding7,6777.9not in edit history
PhoenixNAPnot recordedBuilding7,3607.62024-02-26
Digital Realty Data CenterDigital RealtyBuilding6,2776.52021-09-12

“First mapped” is when OpenStreetMap recorded the facility, not when it was built — OpenStreetMap carries no construction dates. Mapped area means a building floor plate, campus boundary, or construction polygon according to the “Mapped as” column; those quantities are never added together. The megawatt column appears only for buildings and is their floor-area share of a reported national total, not a measurement.