United States
National · 1,988 data centres recorded in OpenStreetMap
Mapped facilities
1,988
on the map today
Floor area
21.19
km² across 1,586 buildings
Share of US load
21,918
MW, inferred upper bound
Water
47.67
million gal/day, inferred
273 of these 1,988 are not mapped as buildings, so no power figure is estimated for them. 196 are campus boundaries covering 81.76 km² of land, and 77 are sites mapped as under construction. The megawatt figure above divides a national total by building floor area, and the area of a land parcel is not floor area. A site still being built consumed none of the electricity that total measures. Both are counted here and left out of the estimate rather than folded into it, so this region's load is understated by however much those represent.
When these appeared on the map
observed, not surveyedtelecom=data_center was not yet in common use — the near-zero readings there describe the tag, not the country. This is a count of what has been mapped, and OpenStreetMap carries no construction dates.117 of these 1,988 facilities do not appear in the curve. The chart counts facilities whose appearance was observed in OpenStreetMap's edit history; one mapped before 2012 has no creation edit to observe. The two numbers answer different questions — how many are on the map now, and how many were watched arriving — and neither is wrong.
Largest named mapped records
by mapped area| Name | Operator | Mapped as | Mapped area m² | Share MW | First mapped |
|---|---|---|---|---|---|
| Fermi Matador | not recorded | Under construction | 23,985,125 | — | not in edit history |
| Project Cardinal | not recorded | Under construction | 4,457,436 | — | not in edit history |
| Meta El Paso Data Center | not recorded | Under construction | 3,282,699 | — | not in edit history |
| Joliet Technology Center | not recorded | Campus boundary | 3,225,950 | — | 2026-06-11 |
| Microsoft Fairwater Phase 2 | not recorded | Campus boundary | 3,147,782 | — | 2026-06-11 |
| Meta Los Lunas Data Center | Meta | Campus boundary | 2,870,676 | — | 2021-11-01 |
| Project Jupiter | Santa Teresa Land LLC;Border Plex Digital Assets LLC dba Acoma LLC;Stargate LLC | Under construction | 2,479,486 | — | 2026-06-20 |
| Google Montgomery Data Center | Google LLC | Campus boundary | 2,472,353 | — | 2023-03-10 |
| Altoona Meta Data Center | Meta | Campus boundary | 2,468,302 | — | 2025-03-19 |
| Project Jade Data Center | not recorded | Under construction | 2,425,956 | — | 2026-07-01 |
| Microsoft Granger Data Center | not recorded | Campus boundary | 2,350,360 | — | not in edit history |
| Meta Eagle Mountain Data Center | Meta | Campus boundary | 2,112,083 | — | 2023-02-23 |
| Meta Bowling Green Data Center | not recorded | Under construction | 1,997,251 | — | 2025-11-29 |
| Meta Montgomery Data Center | not recorded | Under construction | 1,879,996 | — | 2026-03-21 |
| Google Omaha Data Center | Campus boundary | 1,818,664 | — | 2024-12-03 | |
| Apple Data Center | not recorded | Campus boundary | 1,742,168 | — | 2026-07-01 |
| Meta Beaver Dam Data Center | Meta | Under construction | 1,696,551 | — | 2025-11-29 |
| Google New Albany Data Center | Campus boundary | 1,616,081 | — | 2025-08-26 | |
| Gallatin Data Center | Meta | Campus boundary | 1,583,534 | — | 2023-10-07 |
| AWS Canton Data Center | Amazon | Campus boundary | 1,540,462 | — | 2025-12-19 |
| Meta Cheyenne Data Center | Meta | Under construction | 1,505,492 | — | 2025-12-04 |
| Meta Kuna Data Center | Meta | Campus boundary | 1,481,966 | — | 2025-12-04 |
| Meta Mesa Data Center | Meta | Campus boundary | 1,379,701 | — | 2025-06-20 |
| The Barn Data Center | not recorded | Under construction | 1,367,461 | — | 2026-06-11 |
| Microsoft Granger Data Center | not recorded | Campus boundary | 1,347,734 | — | not in edit history |
| Microsoft Fairwater AI Datacenter | not recorded | Campus boundary | 1,334,966 | — | 2026-06-11 |
| Meta Kansas City Data Center | Meta | Campus boundary | 1,298,615 | — | 2025-08-31 |
| Meta Temple Data Center | Meta | Campus boundary | 1,283,950 | — | not in edit history |
| AWS Ridgeland Data Center | Amazon | Campus boundary | 1,235,110 | — | 2026-07-21 |
| DeKalb Meta Data Center | Meta Platforms | Campus boundary | 1,188,532 | — | 2025-12-10 |
| Amazon AWS Data Center | not recorded | Campus boundary | 1,169,289 | — | 2026-02-24 |
| Microsoft Boydton Data Center | Microsoft | Campus boundary | 1,102,062 | — | 2023-12-13 |
| Switch - The Citadel | not recorded | Campus boundary | 1,101,330 | — | 2026-07-04 |
| Microsoft Goodyear Airpark Campus | not recorded | Campus boundary | 1,074,812 | — | 2026-06-24 |
| Google Lockbourne, OH | Under construction | 1,065,016 | — | 2024-09-09 | |
| Google Papillion Data Center | Campus boundary | 1,057,391 | — | 2026-06-30 | |
| Meta LCO 3 Project | Meta | Under construction | 1,042,161 | — | 2026-03-21 |
| Meta Rosemount Data Center | Meta | Under construction | 960,113 | — | 2025-11-29 |
| Microsoft Bison Business Park Data Center | Microsoft | Campus boundary | 928,062 | — | 2026-07-01 |
| Meta New Albany Data Center | Meta | Campus boundary | 924,772 | — | 2026-03-21 |
“First mapped” is when OpenStreetMap recorded the facility, not when it was built — OpenStreetMap carries no construction dates. Mapped area means a building floor plate, campus boundary, or construction polygon according to the “Mapped as” column; those quantities are never added together. The megawatt column appears only for buildings and is their floor-area share of a reported national total, not a measurement.