Static snapshot. This site serves two different things: 1,988 data centres reported by OpenStreetMap contributors nationwide, and 13 sites Helios infers from Arizona parcel records, exported on July 29, 2026. The first is a map of what has been recorded; the second is an argued hypothesis with an evidence chain. This is a point-in-time export, not a live view. See meta.json or the methodology.

United States

National · 1,988 data centres recorded in OpenStreetMap

Mapped facilities
1,988
on the map today
Floor area
21.19
km² across 1,586 buildings
Share of US load
21,918
MW, inferred upper bound
Water
47.67
million gal/day, inferred
273 of these 1,988 are not mapped as buildings, so no power figure is estimated for them. 196 are campus boundaries covering 81.76 km² of land, and 77 are sites mapped as under construction. The megawatt figure above divides a national total by building floor area, and the area of a land parcel is not floor area. A site still being built consumed none of the electricity that total measures. Both are counted here and left out of the estimate rather than folded into it, so this region's load is understated by however much those represent.

When these appeared on the map

observed, not surveyed
09361,871undercounted:the tag was new201520162018201920212022202420252026
Data centres recorded in OpenStreetMap at the end of each month. The hatched stretch is before 2017-01, when telecom=data_center was not yet in common use — the near-zero readings there describe the tag, not the country. This is a count of what has been mapped, and OpenStreetMap carries no construction dates.
117 of these 1,988 facilities do not appear in the curve. The chart counts facilities whose appearance was observed in OpenStreetMap's edit history; one mapped before 2012 has no creation edit to observe. The two numbers answer different questions — how many are on the map now, and how many were watched arriving — and neither is wrong.

Largest named mapped records

by mapped area
NameOperatorMapped asMapped area m²Share MWFirst mapped
Fermi Matadornot recordedUnder construction23,985,125—not in edit history
Project Cardinalnot recordedUnder construction4,457,436—not in edit history
Meta El Paso Data Centernot recordedUnder construction3,282,699—not in edit history
Joliet Technology Centernot recordedCampus boundary3,225,950—2026-06-11
Microsoft Fairwater Phase 2not recordedCampus boundary3,147,782—2026-06-11
Meta Los Lunas Data CenterMetaCampus boundary2,870,676—2021-11-01
Project JupiterSanta Teresa Land LLC;Border Plex Digital Assets LLC dba Acoma LLC;Stargate LLCUnder construction2,479,486—2026-06-20
Google Montgomery Data CenterGoogle LLCCampus boundary2,472,353—2023-03-10
Altoona Meta Data CenterMetaCampus boundary2,468,302—2025-03-19
Project Jade Data Centernot recordedUnder construction2,425,956—2026-07-01
Microsoft Granger Data Centernot recordedCampus boundary2,350,360—not in edit history
Meta Eagle Mountain Data CenterMetaCampus boundary2,112,083—2023-02-23
Meta Bowling Green Data Centernot recordedUnder construction1,997,251—2025-11-29
Meta Montgomery Data Centernot recordedUnder construction1,879,996—2026-03-21
Google Omaha Data CenterGoogleCampus boundary1,818,664—2024-12-03
Apple Data Centernot recordedCampus boundary1,742,168—2026-07-01
Meta Beaver Dam Data CenterMetaUnder construction1,696,551—2025-11-29
Google New Albany Data CenterGoogleCampus boundary1,616,081—2025-08-26
Gallatin Data CenterMetaCampus boundary1,583,534—2023-10-07
AWS Canton Data CenterAmazonCampus boundary1,540,462—2025-12-19
Meta Cheyenne Data CenterMetaUnder construction1,505,492—2025-12-04
Meta Kuna Data CenterMetaCampus boundary1,481,966—2025-12-04
Meta Mesa Data CenterMetaCampus boundary1,379,701—2025-06-20
The Barn Data Centernot recordedUnder construction1,367,461—2026-06-11
Microsoft Granger Data Centernot recordedCampus boundary1,347,734—not in edit history
Microsoft Fairwater AI Datacenternot recordedCampus boundary1,334,966—2026-06-11
Meta Kansas City Data CenterMetaCampus boundary1,298,615—2025-08-31
Meta Temple Data CenterMetaCampus boundary1,283,950—not in edit history
AWS Ridgeland Data CenterAmazonCampus boundary1,235,110—2026-07-21
DeKalb Meta Data CenterMeta PlatformsCampus boundary1,188,532—2025-12-10
Amazon AWS Data Centernot recordedCampus boundary1,169,289—2026-02-24
Microsoft Boydton Data CenterMicrosoftCampus boundary1,102,062—2023-12-13
Switch - The Citadelnot recordedCampus boundary1,101,330—2026-07-04
Microsoft Goodyear Airpark Campusnot recordedCampus boundary1,074,812—2026-06-24
Google Lockbourne, OHGoogleUnder construction1,065,016—2024-09-09
Google Papillion Data CenterGoogleCampus boundary1,057,391—2026-06-30
Meta LCO 3 ProjectMetaUnder construction1,042,161—2026-03-21
Meta Rosemount Data CenterMetaUnder construction960,113—2025-11-29
Microsoft Bison Business Park Data CenterMicrosoftCampus boundary928,062—2026-07-01
Meta New Albany Data CenterMetaCampus boundary924,772—2026-03-21

“First mapped” is when OpenStreetMap recorded the facility, not when it was built — OpenStreetMap carries no construction dates. Mapped area means a building floor plate, campus boundary, or construction polygon according to the “Mapped as” column; those quantities are never added together. The megawatt column appears only for buildings and is their floor-area share of a reported national total, not a measurement.