Static snapshot. This site serves two different things: 1,988 data centres reported by OpenStreetMap contributors nationwide, and 13 sites Helios infers from Arizona parcel records, exported on July 29, 2026. The first is a map of what has been recorded; the second is an argued hypothesis with an evidence chain. This is a point-in-time export, not a live view. See meta.json or the methodology.

Prince William County

County in VA · 74 data centres recorded in OpenStreetMap

Mapped facilities
74
on the map today
Floor area
1.08
km² across 68 buildings
Share of US load
1,120
MW, inferred upper bound
Water
2.44
million gal/day, inferred
6 of these 74 are not mapped as buildings, so no power figure is estimated for them. 3 are campus boundaries covering 0.23 km² of land, and 3 are sites mapped as under construction. The megawatt figure above divides a national total by building floor area, and the area of a land parcel is not floor area. A site still being built consumed none of the electricity that total measures. Both are counted here and left out of the estimate rather than folded into it, so this region's load is understated by however much those represent.

When these appeared on the map

observed, not surveyed
03467201620182019202020212023202420252026
Data centres recorded in OpenStreetMap at the end of each month. The hatched stretch is before 2017-01, when telecom=data_center was not yet in common use — the near-zero readings there describe the tag, not the country. This is a count of what has been mapped, and OpenStreetMap carries no construction dates.
7 of these 74 facilities do not appear in the curve. The chart counts facilities whose appearance was observed in OpenStreetMap's edit history; one mapped before 2012 has no creation edit to observe. The two numbers answer different questions — how many are on the map now, and how many were watched arriving — and neither is wrong.

What the grid here looks like

reported by OSM contributors
Substations
59
69 kV and above
Bulk substations
33
230 kV and above
Highest voltage
500
kV, present in this county
Generating capacity
726
MW across 4 plants

A facility drawing hundreds of megawatts connects at bulk transmission voltage, so the second figure matters more than the first: forty 69 kV yards are not a substitute for one 500 kV substation.

Proximity is not connection. Nothing here shows that any facility has contracted power from any of these substations. That gets settled in interconnection filings Helios cannot read, and in several regions those queues now run for years. A county showing no substations may have none mapped rather than none standing.

Largest named mapped records

by mapped area
NameOperatorMapped asMapped area m²Share MWFirst mapped
NTT VA10NTTBuilding43,43444.9not in edit history
Digital Realty IAD51Digital RealtyBuilding37,89739.2not in edit history
Digital Realty IAD50Digital RealtyBuilding37,89739.2not in edit history
CloudHQ MCC1CloudHQBuilding37,15338.42021-10-27
CloudHQ MCC2CloudHQBuilding32,61833.72021-10-27
Google Mango Farm Building 1GoogleBuilding26,91727.82024-02-19
Google Mango FarmGoogleBuilding26,90727.82024-05-28
Google Mango Farm Building 3GoogleBuilding26,90427.82026-01-05
STACK NVA02DStack InfrastructureBuilding23,96524.82023-07-14
Microsoft Data Center 2MicrosoftBuilding22,95423.72025-11-03
Digital Realty VA4Digital RealtyBuilding21,36822.12021-08-03
Amazon IAD-55Amazon Web ServicesBuilding21,19521.92021-09-14
Equinix DC14EquinixCampus boundary20,703—2023-11-29
Amazon IAD-95Amazon Web ServicesBuilding19,95120.62021-10-26
Amazon IAD-85Amazon Web ServicesBuilding19,94320.62021-10-26
Amazon IAD-100Amazon Web ServicesBuilding19,93820.62021-10-27
Amazon IAD-102Amazon Web ServicesBuilding19,91320.62021-10-27
Amazon IAD-101Amazon Web ServicesBuilding19,91220.62021-10-27
Amazon IAD-105Amazon Web ServicesBuilding19,90620.62023-01-24
Amazon IAD-104Amazon Web ServicesBuilding19,90520.62023-01-24
AWSAmazon Web ServicesBuilding19,76120.42024-02-19
Amazon IAD-106Amazon Web ServicesBuilding19,06419.72023-11-07
Iron Mountain VA-6Iron MountainBuilding16,90117.52024-12-22
Iron Mountain VA-3Iron MountainBuilding16,83217.42024-05-16
STACK NVA05BSTACK InfrastructureBuilding16,77517.4not in edit history
Iron Mountain VA-1Iron MountainBuilding15,21715.72021-10-26
Iron Mountain VA-2Iron MountainBuilding14,74015.32021-10-26
STACK NVA05CSTACK InfrastructureBuilding14,48515.0not in edit history
QTS Manassas DC5Quality Technology ServicesBuilding14,26414.82023-06-27
Amazon IAD-84Amazon Web ServicesBuilding14,18614.72020-07-20
Iron Mountain VA-7Iron MountainBuilding13,92414.42026-05-08
Amazon IAD-94Amazon Web ServicesBuilding13,87314.32024-05-06
Amazon IAD-132Amazon Web ServicesBuilding13,86214.32023-06-12
Amazon IAD-75Amazon Web ServicesBuilding13,84914.32021-10-26
Amazon IAD-96Amazon Web ServicesBuilding13,84914.32021-10-26
Amazon IAD-64Amazon Web ServicesBuilding13,70814.22020-07-20
Amazon IAD-74Amazon Web ServicesBuilding13,70114.22021-10-26
Amazon IAD-73Amazon Web ServicesBuilding13,57914.12021-10-26
Amazon IAD-103Amazon Web ServicesBuilding13,18413.62023-11-29
STACK NVA05ASTACK InfrastructureBuilding12,96913.42026-01-05

“First mapped” is when OpenStreetMap recorded the facility, not when it was built — OpenStreetMap carries no construction dates. Mapped area means a building floor plate, campus boundary, or construction polygon according to the “Mapped as” column; those quantities are never added together. The megawatt column appears only for buildings and is their floor-area share of a reported national total, not a measurement.