Static snapshot. This site serves two different things: 1,853 data centres reported by OpenStreetMap contributors nationwide, and 13 sites Helios infers from Arizona parcel records, exported on July 29, 2026. The first is a map of what has been recorded; the second is an argued hypothesis with an evidence chain. This is a point-in-time export, not a live view. See meta.json or the methodology.

NE

State · 27 data centres recorded in OpenStreetMap

Mapped facilities
27
on the map today
Floor area
0.50
km² across 21 buildings
Share of US load
549
MW, inferred upper bound
Water
1.19
million gal/day, inferred
6 of these 27 are not mapped as buildings, so no power figure is estimated for them. 6 are campus boundaries covering 4.77 km² of land. The megawatt figure above divides a national total by building floor area, and the area of a land parcel is not floor area. A site still being built consumed none of the electricity that total measures. Both are counted here and left out of the estimate rather than folded into it, so this region's load is understated by however much those represent.

When these appeared on the map

observed, not surveyed
01326202020212022202220232024202420252025
Data centres recorded in OpenStreetMap at the end of each month. The hatched stretch is before 2017-01, when telecom=data_center was not yet in common use — the near-zero readings there describe the tag, not the country. This is a count of what has been mapped, and OpenStreetMap carries no construction dates.
1 of these 27 facilities do not appear in the curve. The chart counts facilities whose appearance was observed in OpenStreetMap's edit history; one mapped before 2012 has no creation edit to observe. The two numbers answer different questions — how many are on the map now, and how many were watched arriving — and neither is wrong.

What the grid here looks like

reported by OSM contributors
Substations
561
69 kV and above
Bulk substations
63
230 kV and above
Highest voltage
345
kV, present in this state
Generating capacity
11,872
MW across 107 plants

A facility drawing hundreds of megawatts connects at bulk transmission voltage, so the second figure matters more than the first: forty 69 kV yards are not a substitute for one 500 kV substation. 15 of the plants here carry no capacity tag, so the megawatt total is a floor rather than the region's output.

Proximity is not connection. Nothing here shows that any facility has contracted power from any of these substations. That gets settled in interconnection filings Helios cannot read, and in several regions those queues now run for years. A county showing no substations may have none mapped rather than none standing.

Largest named mapped records

by mapped area
NameOperatorMapped asMapped area m²Share MWFirst mapped
Google Omaha Data CenterGoogleCampus boundary1,818,6642024-12-03
Google Papillion Data CenterGoogleCampus boundary1,057,391before 2012
Sarpy Meta Data Centernot recordedCampus boundary726,2622025-11-27
Sarpy Meta Data CenterMetaCampus boundary579,9802023-02-13
Sarpy Meta Data CenterMetaCampus boundary550,2022021-05-13
Meta Sarpy Data centerMetaBuilding61,90967.82020-09-04
Meta Sarpy Data centerMetaBuilding58,39564.02024-02-21
Meta Sarpy Data centerMetaBuilding58,09163.72024-02-21
Meta Sarpy Data centerMetaBuilding47,85352.52020-09-04
Compute Northnot recordedCampus boundary32,8282024-07-08
GoogleGoogleBuilding27,63330.32024-02-21
GoogleGoogleBuilding27,63130.32024-09-02
GoogleGoogleBuilding27,21529.82024-02-21
GoogleGoogleBuilding26,95729.52025-08-13
GoogleGoogleBuilding26,95429.52025-08-13
GoogleGoogleBuilding26,95229.52025-08-13
Meta Sarpy Data centerMetaBuilding26,59429.12024-02-21
YahooYahooBuilding22,08224.22024-05-14
Travelers InsuranceTravelers InsuranceBuilding16,94618.62024-05-14
GoogleGoogleBuilding14,16615.52020-09-04
Verizonnot recordedBuilding8,1178.92023-10-04
First National Technical CenterFirst National of NebraskaBuilding6,4317.02022-10-20
Union Pacific Jack Koraleski Technology, Research & Development CenterUnion Pacific RailroadBuilding5,0535.52025-06-14
FidelityFidelityBuilding3,7824.22023-04-30
1623 FarnamNews-Press & Gazette CompanyBuilding3,3163.62025-08-28
Verizonnot recordedBuilding1,1001.22023-10-04

“First mapped” is when OpenStreetMap recorded the facility, not when it was built — OpenStreetMap carries no construction dates. Mapped area means a building floor plate, campus boundary, or construction polygon according to the “Mapped as” column; those quantities are never added together. The megawatt column appears only for buildings and is their floor-area share of a reported national total, not a measurement.