VA
State · 405 data centres recorded in OpenStreetMap
When these appeared on the map
observed, not surveyedtelecom=data_center was not yet in common use — the near-zero readings there describe the tag, not the country. This is a count of what has been mapped, and OpenStreetMap carries no construction dates.What the grid here looks like
reported by OSM contributorsA facility drawing hundreds of megawatts connects at bulk transmission voltage, so the second figure matters more than the first: forty 69 kV yards are not a substitute for one 500 kV substation. 42 of the plants here carry no capacity tag, so the megawatt total is a floor rather than the region's output.
Proximity is not connection. Nothing here shows that any facility has contracted power from any of these substations. That gets settled in interconnection filings Helios cannot read, and in several regions those queues now run for years. A county showing no substations may have none mapped rather than none standing.
Largest named mapped records
by mapped area| Name | Operator | Mapped as | Mapped area m² | Share MW | First mapped |
|---|---|---|---|---|---|
| Microsoft Boydton Data Center | Microsoft | Campus boundary | 1,102,062 | — | 2023-12-13 |
| QTS Richmond 1 Data Center | Quality Technology Services | Campus boundary | 538,156 | — | 2023-12-15 |
| QTS Richmond 3 Data Center | Quality Technology Services | Under construction | 454,388 | — | 2026-03-27 |
| True North Data Centers | True North Data Solutions | Campus boundary | 425,795 | — | 2025-05-16 |
| QTS Richmond 2 Data Center | Quality Technology Services | Under construction | 407,798 | — | 2026-03-27 |
| Digital Loudoun Plaza | not recorded | Campus boundary | 265,693 | — | 2022-01-13 |
| PowerHouse CTP-03 | not recorded | Under construction | 261,050 | — | 2026-03-27 |
| Bank of America Data Center | not recorded | Campus boundary | 205,312 | — | 2023-12-15 |
| Google Data Center | Campus boundary | 199,105 | — | 2023-07-22 | |
| NTT Ashburn Campus | not recorded | Campus boundary | 196,595 | — | 2024-12-19 |
| Arcola Tech Park | not recorded | Campus boundary | 161,230 | — | 2021-01-19 |
| Amazon Fadeley III | not recorded | Campus boundary | 153,751 | — | 2023-04-12 |
| CloudHQ Ashburn Campus | not recorded | Campus boundary | 144,296 | — | 2024-12-19 |
| White Oak Technology Park 2 | QTS | Under construction | 139,335 | — | 2026-03-27 |
| Microsoft Data Center | Microsoft | Campus boundary | 137,061 | — | 2021-01-19 |
| Equinix CU2 | Equinix | Campus boundary | 120,768 | — | 2023-12-25 |
| Stonewall Creek Business Park | Campus boundary | 120,008 | — | 2021-10-28 | |
| QTS Ashburn Lockridge | Quality Technology Services | Campus boundary | 115,619 | — | 2026-05-22 |
| Amazon Web Services Datacenter Complex | Amazon Web Services | Campus boundary | 101,083 | — | 2016-12-16 |
| Amazon Web Services | Amazon Web Services | Campus boundary | 94,979 | — | 2016-12-16 |
| QTS Ashburn-Shellhorn | not recorded | Campus boundary | 77,067 | — | 2024-12-19 |
| Digital Loudoun Plaza | not recorded | Campus boundary | 63,782 | — | 2022-01-13 |
| Meta Henrico Data Center | Meta | Building | 56,178 | 61.6 | 2025-05-29 |
| Meta Henrico Data Center | Meta | Building | 54,645 | 59.9 | 2024-09-02 |
| Digital Realty Northern Virginia IAD39 | Digital Realty | Building | 51,025 | 55.9 | 2019-07-30 |
| CyrusOne NVA5 | CyrusOne | Building | 47,097 | 51.6 | 2016-12-16 |
| DBT Data - Harrisonburg Center | not recorded | Campus boundary | 46,986 | — | 2023-12-08 |
| CloudHQ LC1 | CloudHQ | Building | 46,377 | 50.8 | 2020-04-20 |
| CloudHQ LC4 | CloudHQ | Building | 42,791 | 46.9 | 2025-04-28 |
| Digital Realty ACC7 | Digital Realty | Building | 38,042 | 41.7 | 2018-11-27 |
| CloudHQ MCC1 | CloudHQ | Building | 37,153 | 40.7 | 2021-10-27 |
| Digital Realty Northern Virginia IAD44 | Digital Realty | Building | 37,118 | 40.7 | 2024-09-24 |
| Digital Realty Northern Virginia IAD44 | Digital Realty | Building | 37,116 | 40.7 | before 2012 |
| Digital Realty IAD41 (Building P) | Digital Realty | Building | 36,881 | 40.4 | 2020-04-19 |
| CloudHQ MCC2 | CloudHQ | Building | 32,618 | 35.8 | 2021-10-27 |
| VISA Data Center | not recorded | Building | 32,515 | 35.6 | 2020-07-11 |
| Digital Realty ACC9 | Digital Realty | Building | 30,589 | 33.5 | 2018-11-27 |
| Meta Henrico Data Center | Meta | Building | 30,465 | 33.4 | 2024-09-02 |
| Digital Realty ACC5 | Digital Realty | Building | 27,765 | 30.4 | 2016-12-16 |
| Digital Realty ACC4 | Digital Realty | Building | 27,328 | 29.9 | 2016-12-16 |
“First mapped” is when OpenStreetMap recorded the facility, not when it was built — OpenStreetMap carries no construction dates. Mapped area means a building floor plate, campus boundary, or construction polygon according to the “Mapped as” column; those quantities are never added together. The megawatt column appears only for buildings and is their floor-area share of a reported national total, not a measurement.